Level Best Concrete Flooring has been successfully removing and replacing concrete slabs on this site in Daventry and crushing the removed concrete on site to make a brilliant sub base material to place beneath the new floors.
The mobile crushing machine operated by Level Best is producing approximately 300 tonnes per day and the concrete floor replacement teams and using the material to final form the sub base prior to casting the high strength concrete suitably designed for large lifters to traffic over 7 days later. The systems and operations are working seamlessly on the live rail freight terminal which the concrete flooring team will be on site for a two month duration for.
If you would like to know how Level Best Concrete Flooring can assist you with floor removal, replacement and recycle process then please contact us via the contact page on this website thank you.